Granting Consent under the provisions of the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981and Authorization under Bio-medical Waste Management Rules,2016,Hazardous and other Wastes (Management & Transboundary Movement) Rules, 2016 andl Solid Waste Management Rules, 2016 are some of the important functions of the Board. A brief note / guidelines for obtaining the NOC / Consent / Authorization for the entrepreneurs are illustrated below:

Water Act :
Control of water pollution is achieved through administering conditions imposed in consent issued under provision of the Water (Prevention & Control of Pollution) Act, 1974. These conditions regulate the quality and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. The surface and ground water monitoring conducted by the Board indicates that the water quality has improved over the years and that it is now, in general, reasonably good.
Air Act:
Under the Air (Prevention & Control of Pollution) Act, 1981consent of the Board is mandatory for releasing emissions to the atmosphere. The Board issues consent to air polluting industries with conditions to regulate the quality and quantity of emission and stipulate the frequency for monitoring the emissions.
Consent to Establish / Operate:
To establish an industry with potential for water pollution / air pollution; prior consent under the Water Act / Air Act is to be obtained respectively which needs to be obtained in two phases:
Consent to Establish [NOC] This consent is to be obtained prior to establishing any industry or process or plant.
Consent to Operate
[Initial & Renewal]
Once the industry or process plant is established along the required pollution control systems, the entrepreneur is required to obtain consent to operate the unit. The consent is given for a particular period, which is mandatory to be renewed regularly.

Consent to Establish [CTE] fees ::

Slab Total capital investment (in Rupees) Consent to Establish Fees
1. Industries having total investment upto Rs. 5.00 lakhs 2,000/-
2. Industries having total investment exceeding Rs. 5.00 lakhs but not exceeding Rs. 10.00 lakhs. 5,000/-
3. Industries having total investment exceeding Rs. 10.00 lakhs but not exceeding Rs. 20.00 lakhs. 8,000/-
4. Industries having total investment exceeding Rs. 20.00 lakhs but not exceeding Rs. 50.00 lakhs. 12,000/-
5. Industries having total investment exceeding Rs. 50.00 lakhs but not exceeding Rs. 1.00 crores. 50,000/-
6. Industries having total investment exceeding Rs. 1.00 crore but not exceeding Rs. 5.00 crores. 75,000/-
7. Industries having total investment exceeding Rs. 5.00 crore but not exceeding Rs. 10.00 crores. 1,00,000/-
8. Industries having total investment exceeding Rs. 10.00 crores but not exceeding Rs. 50.00 crores. 2,00,000/-
9. Industries having total investment exceeding Rs 50.00 crore but not exceeding Rs. 100.00 crores. 3,00,000/-
10. Industries having total investment exceeding Rs. 100.00 crore but not exceeding Rs. 200.00 crores. 5,00,000/-
11. 200.00 crores above 7,00,000/-

 

Consent to Operate [CTO] fees ::

Slab Total capital investment (in Rupees) Consent Under Air Act Consent Under Water Act
1. Industries having total investment upto Rs. 5.00 lakhs 1,000/- 1,000/-
2. Industries having total investment exceeding Rs. 5.00 lakhs but not exceeding Rs. 10.00 lakhs. 2,500/- 2,500/-
3. Industries having total investment exceeding Rs. 10.00 lakhs but not exceeding Rs. 20.00 lakhs. 5,000/- 5,000/-
4. Industries having total investment exceeding Rs. 20.00 lakhs but not exceeding Rs. 50.00 lakhs. 7,500/- 7,500/-
5. Industries having total investment exceeding Rs. 50.00 lakhs but not exceeding Rs. 1.00 crores. 10,000/- 10,000/-
6. Industries having total investment exceeding Rs. 1.00 crore but not exceeding Rs. 5.00 crores. 25,000/- 25,000/-
7. Industries having total investment exceeding Rs. 5.00 crore but not exceeding Rs. 10.00 crores. 50,000/- 50,000/-
8. Industries having total investment exceeding Rs. 10.00 crores but not exceeding Rs. 50.00 crores. 1,00,000/- 1,00,000/-
9. Industries having total investment exceeding Rs 50.00 crore but not exceeding Rs. 100.00 crores. 2,00,000/- 2,00,000/-
10. Industries having total investment exceeding Rs. 100.00 crore but not exceeding Rs. 200.00 crores. 3,00,000/- 3,00,000/-
11. 200.00 crores above 5,00,000/- 5,00,000/-

* List Of Documents Required.

* Click Here to See the Fee Details.